Toronto Ashbridges Bay Water Treatment Plant | 20.86m | 2s | City of Toronto | B&V

AshNavabi

Administrator
Staff member
Member Bio
Joined
Nov 2, 2020
Messages
8
Reaction score
43
Site Plan Approval submitted in 2009, still "Under Review", without any documents:

Application Number:
09 160691 STE 32 SA
Application Type:
Site Plan Approval
Date Submitted:
20/08/2009
Status:
Under Review
Description:
Site Plan Approval application to construct a biogas cogeneration facility associated with the Ashbridges Bay Treatment Plant. The facility consists of seven outdoor cogeneration engines and a small storage/electrical building. The facility will be operated by Toronto Hydro Energy Services.

From the City website:

"The high-rate treatment facility is designed specifically to provide treatment of CSOs intercepted by the new tunnel system."

Google Street View image of the crane. The other thread on the landform expansion also has pictures of the crane from a distance.

1632239739274.png
 
Article from February 2021 with an overhead view of the site:


A$216 million upgrade at the Ashbridges Bay Water Treatment Plant (ABWTP) was hit by a year’s delay during the excavation phase but is back on track to install an innovative UV disinfectant system.

Nancy Kim, a City of Toronto project manager, says work on the upgrade to the wastewater treatment plant at Lake Ontario by Leslie Street was delayed six months because they discovered a massive sea wall buried along the waterfront.

“It wasn’t on any of the drawings and we had to go back several iterations to find it,” she says. That means it had to be dug up and excavated before the rest of the work could be completed, adding about six months to the schedule. About the same time they found sheet pilings buried along the waterfront close to a service road.

“We had to figure how to get those out without impacting the road which was right up against them so it meant shutting the road down to one lane,” she says, adding they had to go back to the archives to find notes from the 1940s and earlier.

Trouble comes in threes. As they started installing the 1,300 pilings on which the building structures will be placed, engineers began noting they were shifting out of alignment.

“We stopped installation, of course, to find out what was going on,” she says. “We started a geotechnical investigation and found it wasn’t the design of the piles but the bedrock with its Georgian shale in parts, but not uniformly distributed. It’s like a pepper shaker with some in spots.”

With that knowledge in mind the team devised a plan to resolve the pile problem. As of early February, some 1,000 of the 1,300 pilings are in place, Kim says. Cost for the extra work required hasn’t been calculated into the price of the project yet.

The scope of the work at the ABWTP includes a new disinfection building with state-of-the-art UV equipment and sodium hypochlorite/bisulfite chemical systems along with new reinforced concrete disinfection channels housed within a three storey building.

That building includes underground service tunnels and effluent conduits, mechanical service rooms, chemical storage and dosing facilities, electrical power distribution, office space, automation systems and various electrical and instrumentation and control systems.


ashbr.jpg
 
Article from February 2021 with an overhead view of the site:





View attachment 350556

I think this might be a different project - intended to replace chlorination.

AoD
 
Update on Ashbridges Bay Water Treatment Plant upgrades with Photos from Graham Construction.

Last Month the final wall pour on site and beginning of last of suspended slabs to pour 771m3 finishing up in next few weeks

Commissioning and equipment startups have begun and nearing the end of phase 1 completion The UV disinfection and Chemical building are nearly complete with equipment startup scheduled later in the fall.

IMG_2363.jpeg
IMG_2364.jpeg
IMG_2365.jpeg
IMG_2366.jpeg
 
Update on Ashbridges Bay Water Treatment Plant upgrades with Photos from Graham Construction.

Last Month the final wall pour on site and beginning of last of suspended slabs to pour 771m3 finishing up in next few weeks

Commissioning and equipment startups have begun and nearing the end of phase 1 completion The UV disinfection and Chemical building are nearly complete with equipment startup scheduled later in the fall.

View attachment 499239View attachment 499240View attachment 499241View attachment 499242
Hmm. So is the crane gone? Or are what would otherwise be drone shots taken from a still-there crane?

42
 
A new SPA has been submitted for the Integrated Pumping Station:
A Site Plan Control application to permit a new integrated pumping station as part of the existing Ashbridges Bay Water Treatment Plant which is to consist of four new buildings including a pump house, building screen, generator building, and IPS substation. The pump house is proposed to be two-storeys (22m) in height and will contain 1,375 square metres of GFA.

Perspectives:
PLN - Physical or Computer Generated Building Mass Model - null (1)-1.jpg
PLN - Physical or Computer Generated Building Mass Model - null (1)-2.jpg


Plans:
PLN - Architectural Plans - null (25)-01.jpg
PLN - Architectural Plans - null (25)-16.jpg
PLN - Architectural Plans - null (25)-47.jpg
PLN - Architectural Plans - null (25)-55.jpg
 

Back
Top