I'm just going to loop a bunch of properties together since most of this area is all owned by the same developer and this just happens to be the one of the buildings under construction. If the mods want to break it into individual threads that's fine.
Within the lands known as the East Side...
They aren't even close to leasing the first phase. The current leases are for Fuchs, ATS and Dare who collectively have about 325,000 sqft which is about 32% of the first phase. The developer behind this also has another project elsewhere in Cambridge that has over 200,000 sqft still to be...
As YongeBloor mentioned this is a data centre.
The site was originally owned by Blackberry but was sold to Ascent Corp. The site is really split into two different parts. There is the existing building at 17 Vondrau and then the vacant land (25 acres) behind the site which is intended for...
The intent for Vive on this site is to have the next building follow in succession, complete one then move to the next. Phase 3 doesn't have a decision in terms of the ZBA/OPA that was submitted for the extra height but that will be coming in the new year, at which point there will be some...
The second tower is actively rising, they have all the appropriate permits to do so. The pictures I took from April that shows the podium is rather elusive in that the portion you could see from my second picture was just the podium along King, they hadn't done anything where the second tower is...
This project is one of about a dozen projects that are awfully similar in the Northdale area of Waterloo, some are on Urban Toronto some aren't. For the vast majority of these projects they are midrise and have been utilizing precast, typically supplied by Stubbes. The primary target is students...
That would be for this project: https://urbantoronto.ca/forum/threads/toronto-249-west-oak-trail-m-8s-pinemount.41996/
The foundation and site servicing permit was issued on December 11th.
Yes the first 3 are complete, commercial units are occupied in the first two buildings which include a coffee shop, a barber shop, and a pharmacy, commercial for building 3 hasn't been leased yet. Then the building they're working on is the 4th and final building.
There's already a thread for that one on Urban Toronto.
https://urbantoronto.ca/forum/threads/toronto-allen-square-40-9m-10s-axia-geocapital-john-macdonald.36940/
ELM intends to continue with the as approved plans. The permits for underground work for Towers B and C were issued and subsequently those levels were completed (why the crane was up awhile ago). Since then ELM has worked on getting the above grade permits for the next 2 buildings which have...
The only work Auburn is doing is the first 3 buildings. They've been moving some of the piles of gravel around preparing for servicing of the internal roads but you can't really see that without a drone.
Building D is being marketed as Platform at Station Park. The original intent was for Tower C and D to go up together (hence Duo) but for obvious reasons that didn't happen.
They have some building permits in progress for Tower D (foundation/tower) but nothing is being issued imminently...
The first buildings is a joint venture between Corley and Vive with Vive running it (all their typical consultants) the rest of the project is also a JV with Corley however after the ZBA/OPA approval Vive has stepped back and Corley is now making the decisions (different set of consultants not...
The crane on this went up December 5th.
The foundation/site servicing permit was issued November 27th, with the balance of construction permit still under review.
This photo is taken from McLennan Park on December 24th. The site is the crane to the left of the photo. The cluster of buildings...
I'm surprised there wasn't a thread for this one, but I'll provide some of the history for this one.
It was originally made public in early 2022 through an OPA/ZBA application. It was planned to be 3 towers built in 2 phases, phase 1 being a 16 floor tower (Tower C). Phase 2 consisted of 2...