News   Dec 23, 2025
 556     3 
News   Dec 23, 2025
 1.3K     1 
News   Dec 23, 2025
 2.1K     1 

Recent content by matted

  1. M

    Toronto Concord Sky | 300.2m | 85s | Concord Adex | Kohn Pedersen Fox

    The started back at the site in late Spring early summer this year by the time the transfer to CA took place. The staging slab for the site was not completed until the mid summer at the site. They could not fully excavate untill that was completed. They really didn't commence the main dig until...
  2. M

    Toronto U of T: Landscape of Landmark Quality | ?m | 1s | U of T | MVVA

    They have dont seem to be using a tower crane. This large area without the use of a tower crane is also likely a major reason why.
  3. M

    Toronto Pinnacle Lakeside Phase 2 | 147.6m | 43s | Pinnacle | Hariri Pontarini

    Permits for water discharge..groundwater
  4. M

    Mississauga M3 at M City | 260.29m | 77s | Rogers Real Estate | Arcadis

    Looks close to 5 levels. 1 more to go...
  5. M

    Mississauga Oro + Edge Towers | ?m | 50s | Solmar | Rosario Varacalli

    With the next phase you have another 5-6 years to look forward to
  6. M

    Mississauga Oro + Edge Towers | ?m | 50s | Solmar | Rosario Varacalli

    Take a closer look. The ramp into the hole is the only way that they can pour concrete. They don't have a permit to accept concrete from any other area of the site. If you don't have a clue on construction logistics or site logistics because of permit delays (which this site is known to have...
  7. M

    Mississauga M3 at M City | 260.29m | 77s | Rogers Real Estate | Arcadis

    They are waiting for the shoring to start. Permits were just issued. Likely some activity will start there next week.
  8. M

    Mississauga Oro + Edge Towers | ?m | 50s | Solmar | Rosario Varacalli

    They are using shot crete here. Both towers are P4.
  9. M

    Mississauga M3 at M City | 260.29m | 77s | Rogers Real Estate | Arcadis

    Shale starts at below P1. I know what I am talking about
  10. M

    Mississauga M3 at M City | 260.29m | 77s | Rogers Real Estate | Arcadis

    Where they have tarped is where the shoring and shot crete is.
  11. M

    Mississauga M3 at M City | 260.29m | 77s | Rogers Real Estate | Arcadis

    M1 and M2 had shoring. Check your facts. They drill the piles to the top of the rock. Notice how short they are for such a deep excavation.
  12. M

    Mississauga M3 at M City | 260.29m | 77s | Rogers Real Estate | Arcadis

    There is shoring on 3 sides of the site. They don't have a permit which appears why they are only concentrating in the middle area.
  13. M

    Mississauga M3 at M City | 260.29m | 77s | Rogers Real Estate | Arcadis

    No drill. You drill to the top of the rock.

Back
Top