4 months to finish concrete/ remove crane. Puts a may/ June, plus 3 months for elevator/ mechanical commissioning. Probably the earliest for lower floors would be September.Hi, considering it’s a 50 storey tower, and they are at floor 33/34 slab level and considering centre court never does interim occupancy( they directly do final closing)
What could be a reasonable closing/ occupancy month/year?
TIA