As the earlier incident occurred during the unscored phase of testing, the timeline for RSD did not ‘restart’ to day 1 but rather resumed as unscored testing once the trains were on the line again,” a spokesperson told Global News.![]()
More than 30 days after entering final tests, Eglinton Crosstown LRT still being assessed - Toronto | Globalnews.ca
On Oct. 7, provincial transit agency Metrolinx announced the Crosstown had started revenue service demonstration, a key 30-day testing process.globalnews.ca
“Should an issue occur during the scored phase, we would restart the specific week of scored testing but would not need to re-do the unscored portion.” The agency would not tell Global News how many days were left, but said the light rail route had now entered the scored testing phase.
20205 maybe still in play? Also no mention of that bedding in period hmmmm...
Edit: I was being sarcastic here. I know the 2025 dreams are probbaly dead. Metrolinx needs to be transparent about delays like the rem in montreal and the o train in ottawa have been recently. It serves no one other than the ford to pretend that everything is alright.