October 19
More up on my site
Took a walk up tp Kingsbridge as I had no service and nothing to do until 6pm to have a look at the corridor. Nothing new until the wye area. The base of the wye are for the retraining wall poured with the top still to be pour. A n opening is in the Hurontario side retraining wall to allow equipmet and concrete truch to gain access to the wye area, Saw no concrete for the guideway base for the wye area that I could see.
Formwork in place for the top of the ramp retraining was and could not see if concrete has been poured for it.
Not sure where the ramp will connect to Hurontario by how the area is dug up. Could be south of the traffic light pole, the Traffic pole or north of it based on the digging and the placing of the EPS Geofoam Blocks. There more of the existing and new EPS Geofoam Blocks noth of the 403 westbound off ramp.
Looking at the EPS Geofoam Blocks got me thinking if they were place in the ramp area as well the Rathburn ramp since I saw neither of them been backfill.
New curb has been porred for the westbound on ramp for the 403 with a ramp for pedestrians the ramp at the south end now all the hydro underground work is done from Hillcrest to the ramp area as well to the substation.
Was planning on looking at a few other things but lookes like rain was coming and came as I hit Sq One.