Hydro had 4 trucks and crew working on the supported pole at Central Pkwy to and there is a 3rd excavated site there as well.
No one working at Counteypark today,
No concrete pour for the Derry Station formwork.
Some concrete has been pour for Topflight diamond area and on track to open on the 15th as plan. Saw no change for the OMSF guideway rebuilt with someone maning the site these days. Will not be surprise to see trackwork on Topflight torn up like the OMSF guideway.
The 407 westbound on ramp area is being clear and graded for the ramp as well the new area where the ramp will be move to for the new sharp curve.
The only thing I saw new in Brampton was at Ray Lawson with a hole been dug where new paving took place some month ago.
Hydro had 4 trucks and crew working on the supported pole at Central Pkwy to and there is a 3rd excavated site there as well.
No one working at Counteypark today,
No concrete pour for the Derry Station formwork.
Some concrete has been pour for Topflight diamond area and on track to open on the 15th as plan. Saw no change for the OMSF guideway rebuilt with someone maning the site these days. Will not be surprise to see trackwork on Topflight torn up like the OMSF guideway.
The 407 westbound on ramp area is being clear and graded for the ramp as well the new area where the ramp will be move to for the new sharp curve.
The only thing I saw new in Brampton was at Ray Lawson with a hole been dug where new paving took place some month ago.