As seen from last few photos by WillWu today, the FlyingTables are now being utilized! They seem to be starting Table-Form/Flying-Form (something TMG builder specialize in),... hence concrete forming should progress at about 1 floor every 1-1.5 weeks,.... thus, I would expect this project to top out in early-Spring 2019 and complete by around Summer-Fall 2019. And then Bazis will ride off into the sunset back to Kazakhstan.