Interesting - it would appear we will be getting a new terminal, per the May WT Board Meeting CEO report:
http://www.waterfrontoronto.ca/uploads/documents/ceo_report___public_1.pdf (p. 8)
AoD
Jack Layton Ferry Terminal and Harbour Square Park
With support from City of Toronto’s Parks, Forestry and Recreation department and Councillor McConnell’s office, Waterfront Toronto will be hosting a design competition for the Jack Layton Ferry Terminal and Harbour Square Park. The competition RFQ is scheduled to be issued in late July 2014, with short-listed candidates selected by the end of September 2014. The short-listed candidates will then compete in an 8 week design competition, with a successful proponent being selected by mid-December. The successful proponent will then be awarded a contract to refine the design, complete working drawings and provide construction oversight for Phase I of the overall Master Plan
http://www.waterfrontoronto.ca/uploads/documents/ceo_report___public_1.pdf (p. 8)