It has been four months since September when Menkes Developments marked the start of construction for the Waterfront Innovation Centre in Toronto's East Bayfront area. Shoring activity that began the first stage is now wrapping up, and excavation has now begun for the new 12-storey, 400,000 ft², Sweeny &Co Architects-designed office development.

Shoring at the west side of the Waterfront Innovation Centre site, image by Forum contributor Full Metal Junkie

The site is bisected by a short north-south stretch of Dockside Drive. Shoring activity is now proceeding on the smaller footprint of the western portion, where a drilling rig (above) continues to bore holes for the site's caisson wall shoring system. Meanwhile, excavation is now progressing on the much larger eastern portion east of the road (below).

Excavation for the Waterfront Innovation Centre site, image by Forum contributor Full Metal Junkie

Crews are digging to a three-storey depth for the building's underground garage, to hold 197 spaces. The dig is furthest along just east of Dockside Drive, where the pit has been excavated roughly two levels deep so far, and requiring a horizontal drilling rig to install a first row of tiebacks to anchor the shoring walls to the surrounding earth.

Excavation for the Waterfront Innovation Centre site, image by Forum contributor Full Metal Junkie

Tieback drilling has since progressed to the east end of the site, closest to Knapp Lane. The image below shows the horizontal drilling rig used for tiebacks sitting idle, while tubes for the site's de-watering drape over the fence.

Horizontal drilling rig at the Waterfront Innovation Centre site, image by Forum contributor Full Metal Junkie

The project—part of a larger regeneration of the area overseen by Waterfront Toronto—is targeting a 2021 completion date, set to house at least 2,000 workers upon opening. WPP will be the building's lead tenant, with the the Canadian head offices for the multinational e-commerce, advertising, online media, public relations, communications, and branding services giant to occupy 260,000 square feet of the building.

You can get more information about and see more renderings of the Waterfront Innovation Centre in our database file, linked below. You can get in on the discussion in our associated Forum thread, or leave a comment in the space provided on this page.

* * *

UrbanToronto has a new way you can track projects through the planning process on a daily basis. Sign up for a free trial of our New Development Insider here.

Related Companies:  BGO, Kramer Design Associates Limited, LRI Engineering Inc., Menkes Developments, Peter McCann Architectural Models Inc., Sweeny &Co Architects Inc., Trillium Architectural Products