Toronto The Well | 174.03m | 46s | RioCan | Hariri Pontarini

^that's a continuation of the office space from the main tower

support structures there for the terracotta fins
 
The area in question - you can see the fins in the rounded sections at either end

Building-f.png
 
Friday, December 18. Another week, and another rise in the level of construction for the office tower. Also, busy pouring concrete on a Friday afternoon.

Ten days since the last step up to the 34th Floor, the forms on the west side of the office tower have started their migration up to the 35th Floor.

Cycle times per floor over the past months since early May have been:

Date.................Floor.........Days
May 1................19................-
May 28..............20................27
June 12.............21................15
June 25.............22................13
July 10...............23................15
July 24...............24................14
August 10.........25................18 (Includes the August long holiday weekend)
August 21.........26................11
Sept. 3................27................13
Sept. 21..............28...............18 (Includes the Labour Day holiday long weekend)
October 9...........29...............18
October 23........30...............14 (Includes the Thanksgiving Day holiday long weekend)
November 5......31...............13
November 13....32................8
November 25....33..............12 (This time period spans two weekends)
December 8.......34..............13 (This time period spans two weekends)
December 18.....35..............10

20201218_145844.jpg
 
...least it's not pretend "curve" glass which dot many "curvy" developments. >.<
 
I'm in a friggin' time-warp but at least my ancient "green whine" avatar is still current (sadly the image now crops out the missing UT-branded bottle of green whine and a parrot).

Permission to start a Well-intentioned appreciation thread for this transformative project on the former waste-land of Front Street West.
 