Toronto Ryerson University: Daphne Cockwell Health Sciences Complex | 105.76m | 27s | Ryerson University | Perkins&Will

Looks like the second crane will be installed this weekend!

upload_2016-9-23_14-2-1.png
 

Attachments

  • upload_2016-9-23_14-2-1.png
    upload_2016-9-23_14-2-1.png
    29.1 KB · Views: 1,721
Most recent construction update from the project website:
http://ryersonbuilds.ryerson.ca/daphne-cockwell-health-sciences-complex/

November 25, 2016:
With the pleasant weather this fall, work on the site has been progressing
well. All excavation is now complete, as is the site hoarding on all sides.
Both cranes are now in place, and crews are working hard on pouring
concrete; they’ve reached Lower Level 1 on the south side of the building
and Lower Level 3 on its north side. Concrete pouring will continue through
the coming weeks, with the project expected to hit “grade-level” – a
significant milestone in any construction project, when the building reaches
ground-level — in mid-January.
 
An incremental update 2 days later from same vantage point, but I feel like they are progressing well.

IMG_20170120_161411.jpg
 

Attachments

  • IMG_20170120_161411.jpg
    IMG_20170120_161411.jpg
    1.1 MB · Views: 502

Back
Top