Toronto Life Condos | 46.33m | 13s | Chestnut Hill | BDP Quadrangle

I was expecting to see a near completion on this project since its been a few months since I was last there and taken back how far it behind. I understand there been a lot of labour issues to the point 3-4 different crews have work this site so far.

When you look to the north one block and see the Balliol Park tower 5 times taller than this one in the same time frame, you know there a site problem.

I have yet to do Sept 5 shots yet
 
Sept 5
You know a site is having issues when a building a block away that started off after this one is being top off a floor higher than this one.
20665610404_e7cbe48084_b.jpg

21100238520_1efc41b14b_b.jpg

20665653394_e26e82d19b_b.jpg

21262098436_0109339639_b.jpg

20667246203_4c3cbf41db_b.jpg
 
November 14th:

life1.jpg
life2.jpg
life3.jpg
life4.jpg
life5.jpg
 

Attachments

  • life1.jpg
    life1.jpg
    410.9 KB · Views: 1,459
  • life2.jpg
    life2.jpg
    368.1 KB · Views: 1,452
  • life3.jpg
    life3.jpg
    452.9 KB · Views: 1,449
  • life4.jpg
    life4.jpg
    313 KB · Views: 1,454
  • life5.jpg
    life5.jpg
    428.5 KB · Views: 1,445
December 23rd:

20151223_094148.jpg
20151223_094207.jpg
20151223_094227.jpg
20151223_094251.jpg
20151223_094312.jpg
 

Attachments

  • 20151223_094148.jpg
    20151223_094148.jpg
    417.8 KB · Views: 1,213
  • 20151223_094207.jpg
    20151223_094207.jpg
    436.7 KB · Views: 1,205
  • 20151223_094227.jpg
    20151223_094227.jpg
    459.4 KB · Views: 1,178
  • 20151223_094251.jpg
    20151223_094251.jpg
    346.5 KB · Views: 1,201
  • 20151223_094312.jpg
    20151223_094312.jpg
    420.1 KB · Views: 1,168
January 17th update:

20160117_110730.jpg
20160117_110800.jpg
20160117_110833.jpg
20160117_110837.jpg
20160117_110843.jpg
 

Attachments

  • 20160117_110730.jpg
    20160117_110730.jpg
    466.1 KB · Views: 1,092
  • 20160117_110800.jpg
    20160117_110800.jpg
    341.3 KB · Views: 1,073
  • 20160117_110833.jpg
    20160117_110833.jpg
    364.6 KB · Views: 1,096
  • 20160117_110837.jpg
    20160117_110837.jpg
    439.6 KB · Views: 1,132
  • 20160117_110843.jpg
    20160117_110843.jpg
    395.2 KB · Views: 1,067
Today:

IMG_1879.JPG
IMG_1882.JPG
IMG_1883.JPG
IMG_1885.JPG
 

Attachments

  • IMG_1879.JPG
    IMG_1879.JPG
    218.5 KB · Views: 927
  • IMG_1882.JPG
    IMG_1882.JPG
    281.9 KB · Views: 902
  • IMG_1883.JPG
    IMG_1883.JPG
    447.2 KB · Views: 952
  • IMG_1885.JPG
    IMG_1885.JPG
    233.9 KB · Views: 908
I'm trying to imagine that this building is going to look better when it's complete, but that's feeling like a greater stretch than my imagination has had in a while, and it just may snap.
 
This building will actually be 14 stories, 156 suites.

Proposal of draft plan of condominium approval related to a 14-storey plus mechanical penthouse apartment building containing 156 suites, 5 levels of underground parking including a commercial parking garage
Proposed Use --- # of Storeys 14 # of Units 156
Applications:
Type Condominium Approval
Number 16 112136 STE 22 CD
Date Submitted Feb 3, 2016
Status Under Review
 

Back
Top