Toronto Beacon Condos | 124.66m | 35s | Sorbara | Wallman Architects

Seem to be forming ceiling for 33rd floor now. 2 more floors to go (say 1.5 week each) then add a month for mechanical and top. About 2 more months to top out and finish forming (end of March?),... then add 6 months to occupancy looking around end of September? Occupancy usually in phases,... while some of lower floors are wrapped, there's nothing on podium,... best would be Late summer early Fall. For retail I'm seeing Summer and end of year availability.

IMG_0400.JPG


IMG_0412.JPG
 

Attachments

  • IMG_0400.JPG
    IMG_0400.JPG
    204.2 KB · Views: 656
  • IMG_0412.JPG
    IMG_0412.JPG
    216.8 KB · Views: 850
A couple of more from today.

IMG_8163.JPG
IMG_8161.JPG
IMG_8162.JPG
 

Attachments

  • IMG_8163.JPG
    IMG_8163.JPG
    173.9 KB · Views: 604
  • IMG_8161.JPG
    IMG_8161.JPG
    193.8 KB · Views: 609
  • IMG_8162.JPG
    IMG_8162.JPG
    212.5 KB · Views: 592

Back
Top