100 Broadway 
100 Broadway Avenue, Toronto
Developer: Cromwell Property Management


100 Broadway | 113m | 36s | Cromwell | IBI Group

AlbertC

Senior Member
Joined
Apr 24, 2007
Messages
4,072
Reaction score
1,679
Location
Davenport
Chalk up another one for the Yonge & Eg area.

http://app.toronto.ca/DevelopmentApplications/associatedApplicationsList.do?action=init&folderRsn=3832201&isCofASearch=false

223 REDPATH AVE
Ward 25 - North York District

The proposed development consists of a five-storey podium and a 29-storey point tower stepped back from the street and podium edge to maintain the visual prominence of the podium. The proposed development is comprised of 329 residential dwelling units, including 52 replacement rental units, and 120 square metres of non-residential gross floor area in the building podium. The total proposed gross floor area is 19,700 square metres, resulting in a density of approximately 13.4 FSI.
 

ProjectEnd

Senior Member
Joined
May 28, 2007
Messages
8,139
Reaction score
7,104
The application includes 100 Broadway as well. I guess they plan to remove the existing 10 storey building and two storey house / rental and construct the new structure in their place.

It's also 34 storeys (107m) total.
 

Armour

Senior Member
Joined
May 15, 2015
Messages
1,720
Reaction score
368
The application includes 100 Broadway as well. I guess they plan to remove the existing 10 storey building and two storey house / rental and construct the new structure in their place.

It's also 34 storeys (107m) total.
Any idea who the architect is?
 

interchange42

Administrator
Staff member
Joined
Apr 23, 2007
Messages
21,615
Reaction score
14,987
Location
by the Humber
So, to explain what's going on based on that link above…

This development was appealed to the OMB based on the City not having rendered a decision within the 120 time frame. The City, following a pre-hearing this January, received a settlement offer from the developers in May. The settlement was accepted by the July 4 Council meeting, but the details are being kept confidential until such time as this goes back to the OMB in November for a ratification hearing.

42
 

DonValleyRainbow

Senior Member
Joined
Mar 5, 2014
Messages
2,830
Reaction score
1,825
Location
Kay Gardner Beltline Trail
So, to explain what's going on based on that link above…

This development was appealed to the OMB based on the City not having rendered a decision within the 120 time frame. The City, following a pre-hearing this January, received a settlement offer from the developers in May. The settlement was accepted by the July 4 Council meeting, but the details are being kept confidential until such time as this goes back to the OMB in November for a ratification hearing.

42
Thanks. SO much more helpful.
 

PMT

Senior Member
Joined
Jul 13, 2016
Messages
2,750
Reaction score
4,483
Location
Turanna
So, to explain what's going on based on that link above…

This development was appealed to the OMB based on the City not having rendered a decision within the 120 time frame. The City, following a pre-hearing this January, received a settlement offer from the developers in May. The settlement was accepted by the July 4 Council meeting, but the details are being kept confidential until such time as this goes back to the OMB in November for a ratification hearing.

42
OMB decision: http://www.omb.gov.on.ca/e-decisions/pl160910-Jan-22-2018.pdf
 

Rasim

New Member
Joined
May 31, 2017
Messages
8
Reaction score
5
There are 2 on going construction at broadway and redpath area. (Citylights and 150 Redpath). Apparently this will be the 3rd. Traffic will be much more crazy.
 