So basically, this project is dead before it is even proposed? Why go through all this hassle if they know it isn't going to happen?

The province said "give us a plan so we can consider funding it" rather than saying directly no. The city is kinda obligated to prepare a plan and submit it. Odds of the province funding it seem very low; Toronto also needs to ask for ~$4B for Line 2 funding to make SSE a reality (rolling-stock, ATO, yard improvements).
 

kamira51

Active Member
Member Bio
Joined
Jun 25, 2020
Messages
301
Reaction score
445
Location
Caledon East
So basically, this project is dead before it is even proposed? Why go through all this hassle if they know it isn't going to happen?

The province said "give us a plan so we can consider funding it" rather than saying directly no. The city is kinda obligated to prepare a plan and submit it. Odds of the province funding it seem very low; Toronto also needs to ask for ~$4B for Line 2 funding to make SSE a reality (rolling-stock, ATO, yard improvements).
The conservatives could put that on their election platform.
 

duffo

Active Member
Member Bio
Joined
Sep 17, 2020
Messages
103
Reaction score
265
what about the surtax for the Scarborough Subway that now is being paid for by the province? is that the $1B @rbt is referring to? if not, couldn't it be re-allocated?
 

JSF-1

Active Member
Member Bio
Joined
Feb 27, 2018
Messages
567
Reaction score
1,100
Location
Woburn
The conservatives could put that on their election platform.
I doubt will see the Cons willingly fund this project. It's an LRT that runs down the middle of the road in Scarborough so that alone throws up a lot of red flags. As well the Cons are already talking about spending a lot of money on transit as it is, I doubt they are willing to pony up any more; especially for a road bound LRT. They won't cancel it, but I doubt they will fund it. The EELRT will be another Hamilton situation where either the City will need to find a way to fund it alone, the feds step in and force the provinces hand, or we just hope the Cons loose the next election since the Liberals and NDP will no doubt be willing to fund the project.
 

Rainforest

Senior Member
Member Bio
Joined
Mar 23, 2008
Messages
4,673
Reaction score
2,479
That $4.4B price tag may be somewhat overstated.

Just like Hamilton LRT. When the province didn't want to fund it and the Feds were not at the table, the price tag was very high. Once both the province and the Feds came on board, the price went down.
 

ARG1

Senior Member
Member Bio
Joined
May 28, 2020
Messages
1,243
Reaction score
3,241
Location
North Toronto
That $4.4B price tag may be somewhat overstated.

Just like Hamilton LRT. When the province didn't want to fund it and the Feds were not at the table, the price tag was very high. Once both the province and the Feds came on board, the price went down.
Pretty sure the Hamilton LRT's price tag went down because the feds and province agreed to only pay the capital costs meanwhile the city had to fork over the operations cost, so when they announced the funding deal, the numbers only added up to that cost. Part of what made the previous price tag so high is that it included everything including operations and maintenance because the previous deal under the liberals was that they would pay for all of it.
 

Rainforest

Senior Member
Member Bio
Joined
Mar 23, 2008
Messages
4,673
Reaction score
2,479
Pretty sure the Hamilton LRT's price tag went down because the feds and province agreed to only pay the capital costs meanwhile the city had to fork over the operations cost, so when they announced the funding deal, the numbers only added up to that cost. Part of what made the previous price tag so high is that it included everything including operations and maintenance because the previous deal under the liberals was that they would pay for all of it.

Ah, OK. I didn't realize the previous price tag included the operations and future maintenance.
 

rbt

Senior Member
Member Bio
Joined
Apr 25, 2007
Messages
6,881
Reaction score
2,686
That $4.4B price tag may be somewhat overstated.

Maybe but the report says it excluded maintenance and operations. It was a Toronto generated number rather than something Metrolinx provided.


I can see some bridge work that this project might incur which will probably be done anyway, but that'll be relatively small.

The MSF ($500M?) is included. Toronto bus type projects often don't include bus maintenance facility costs.
 

allengeorge

Active Member
Member Bio
Joined
Jun 27, 2019
Messages
880
Reaction score
2,066
IIRC the two things that increased the price were the SSE subway (which required a tunnel to be built?) and the MSF.

I also can’t remember offhand if the $4.4B was for both phases (ie all the way to Malvern or not).

I would like to see this built; it’s a good local complement to the SSE and would go through some neighbourhood improvement areas.
 

smallspy

Senior Member
Member Bio
Joined
Nov 27, 2009
Messages
4,512
Reaction score
4,651
The MSF ($500M?) is included. Toronto bus type projects often don't include bus maintenance facility costs.
That's because there are already a lot of bus garages in the GTA, and getting the vehicles to and from it is as simple as making sure that there are roads between the route and the garage.

An MSF for rail transit is a far more involved proposition, as there are far fewer of them already built and as the line needs a physical connection to it - and so it's location is usually less than ideally suited for that kind of facility.

Dan
 

Rainforest

Senior Member
Member Bio
Joined
Mar 23, 2008
Messages
4,673
Reaction score
2,479
Maybe but the report says it excluded maintenance and operations. It was a Toronto generated number rather than something Metrolinx provided.


I can see some bridge work that this project might incur which will probably be done anyway, but that'll be relatively small.

The MSF ($500M?) is included. Toronto bus type projects often don't include bus maintenance facility costs.

The MSF in the east end will be needed, and will be useful for both EELRT and ECLRT.

But even accounting for that .. $3.9B for a 15-km long mostly surface line sounds like a lot. That's $260M / km, a lot more than for Finch West which came at something like $120M / km with 2 underground termini.
 

ARG1

Senior Member
Member Bio
Joined
May 28, 2020
Messages
1,243
Reaction score
3,241
Location
North Toronto
The MSF in the east end will be needed, and will be useful for both EELRT and ECLRT.

But even accounting for that .. $3.9B for a 15-km long mostly surface line sounds like a lot. That's $260M / km, a lot more than for Finch West which came at something like $120M / km with 2 underground termini.
Well it does have a few underground stations planned, but even then, this is way too expensive for what it is.
 

Rainforest

Senior Member
Member Bio
Joined
Mar 23, 2008
Messages
4,673
Reaction score
2,479
Well it does have a few underground stations planned, but even then, this is way too expensive for what it is.

I think EE LRT and FW LRT are comparable in that.

FW: 11 km length, underground termini at Keele and at Hwy 7, all the rest on surface.

EE: 15 km length, underground terminus at Kennedy, probably tunneled to east of Brimley with an underground station at Brimley, and one more underground station where it crosses Lawrence. The ratio of surface to underground is about same.
 