Allandale25
Senior Member
Blog post by Metrolinx with pictures:
Cedarvale won't be ready by next year, so why bother
unfortunately thats a bit too optimistic of a plan for toronto unfortunately... ?
Originally claimed 2015 assuming it started right away. Which is believable as the TYSSE started main construction in 2011 and finished 2 years later in Dec 2017. It started a couple years late cause of funding issue too as utilities relocation started in 2008. They decided to spread out the cash flow and build the tunnels first which is the main problem. P3 isn't the biggest issue.
Compare
TYSSE (2011-2017) 6 years:
Tunneling: 2011-2013
Station construction: 2011-2016 (death at York U and TTC mismanagement led to delays)
Station finishing: 2015-2017
Track installation: 2014-2016
First train testing: 2017
Opening: 2017
Crosstown (2013-2022?) 9 years:
Tunneling: 2013-2016
Station construction: 2018-2022?
Station finishing: 2019/2020-2022? (Mt Dennis+Keelesdale started last year)
Track installation: 2019-2021?
First train testing: 2019
Opening: 2022?
Now if the Crosstown was phased like TYSSE:
Tunneling: 2013-2015 (Buy 6 TBMs instead of 4, start all tunneling at the same time)
Station construction: 2013-2018 (Start tunneling along with station box construction)
Station finishing: 2017-2019
Track installation: 2016-2018
First train opening: 2019
Opening: 2019!
This takes in account of delays that they face at Eglinton as Downsview Park, York U and Pioneer Village had problems too. So if TTC were to build the line in the traditional way with funding of course, we'll be riding it now. Nevermind, I forgot there's no trains!
A 2025 opening for Eglinton West LRT to Renforth is totally possible. 2027/28 opening would be possible for the Ontario Line if they don't gown down the Crosstown path.
Crosstown won’t open on time? I’m shocked. Shocked!
Delays of this sort happen. The real story is in ML’s secretiveness and lack of transparency. ML seems to believe its own press releases.If they can just keep denying, it will open on time......
The thing to watch is how ML feeds its contractor to the press. The P3 process will be the victim.
No contractor is going to sign up for a P3 in the future without some very tight language and very large contingencies.
- Paul
^Let’s see if they can actually connect the dots. Was the alleged 15 month late start due to lack of approvals? Sounds like that delay happened after the contract was let, ie not as a result of an excessive EA process. Similarly, did the contractor only achieve 84% of schedule because approvals were holding things up? Or was that attributable to other things - labour supply, materiels, engineering, logistics, discovery work?
I sure hope they aren’t saying they will speed up the design/engineering piece. Nobody wants a substandard design. So far, the politicians are the ones using napkins and crayons, the engineers are using proper tools.
- Paul
On projects I work on for a transit company, about half of the timespan of any given project is put in for decision making (well, basically lack of decision making). Overreaching governance is a major issue in delays for public projects.




