From the agenda of the BIFAC committee of TCHC (Sept meeting) we learn this existing 7-storey, 147 unit building is set to get a deep re-fit and re-clad at a cost estimated at ~12M


This is the building as it exists today.

1663252059561.png


This building is located between Main and Victoria Park on Kingston Road, on the north side of said road.

This project is thread-worthy both because of the change in appearance, but also the scale of the reno, which will deliver tenants air conditioning.

Details of the changes from the above linked report are below:

1663252170631.png

Estimated duration; 36 months.

No renders are available in the report; however, there are renders on the Enform site:

1663252389845.png


1663252407381.png
 