Oakville ClockWork Phases 3 & 4 | 43.92m | 12s | Mattamy Homes | KNYMH

Branden Simon

Senior Member
Member Bio
Joined
Apr 30, 2018
Messages
1,878
Reaction score
6,283
Location
Hamilton
Here’s the plan for future Clockwork’s 4, 5 and 6 with building #4 will have 12-Storey with 143 units, building #5 will have 7-Storey with 182 units and building #6 with 178 units.
IMG_1924.jpeg
IMG_1925.jpeg
IMG_1926.jpeg
IMG_1927.jpeg
IMG_1928.jpeg
IMG_1929.jpeg
IMG_1930.jpeg
IMG_1923.jpeg


More elevation renderings for clockwork 4-6 https://www.oakville.ca/getmedia/1d...24ef638a20/sp-130800301-ElevationsPlan-S1.pdf
 
According to RENX (https://renx.ca/the-laurels-is-first-of-three-fall-condo-launches-for-mattamy), construction of building 4 is anticipated to start in April 2025.

Additionally, the Town is looking at:
  1. Increasing the separation distances between proposed buildings and the properties along Aymond Crescent;
  2. Enhancing landscaping along the northern property line;
  3. Reducing and/or redistributing the height and floor area of proposed buildings; and
  4. Reorienting proposed buildings further west and south on the subject lands.
Which was discussed at a recent council meeting on December 9th.
 
Following the changes requested by the town (see above comment) being brought up with Mattamy Homes, Mattamy has made some minor adjustments to the plan for phase 3 of Clockwork (buildings 4, 5, and 6). Bulding 5 (the 7 storey) had its length reduced by 6.3m on the east side, resulting in building 6 increasing in size to maintain the GFA of the entire phase. Additionally, landscaping has been improvement on the north side of the site, between building 5 and the SFHs right north of it, with proposed additional height on fencing between the two sites and trees for privacy. The letter from Mattamy to the town regarding these changes can be found here.
Updated site plan:
1738094175816.png
 
Well this is sad to see... an updated Site Plan Submission from this month shows that the amenity lawn has been removed and replaced with surface parking (similar to the park that was initially proposed in Oakville Yards, just a little west of this one), in addition to a bunch more parking all around the loop in the middle:
1748385809201.png

There is also some (incredibly) minor changes to the elevation plans.
 
The site for building 4 (which was used as a building 3 construction staging area) has been cleared, some gravel has been placed on site, and a tent with chairs and tables has been setup. Looks like a groundbreaking ceremony...
20251008_152643.jpg

The only thing to 100% confirm its a groundbreaking are excavators on site, which I assume will come soon (sometime later this week?).

Its a bit confusing though, since I can't find any issued permits for the site and I highly doubt Mattamy has been able to sell the required amount of units.
 
Update: The tent was removed today, guess there won't be a groundbreaking just yet (unsurprisingly). Wonder what event was held here though...
 

Back
Top