    Toronto The View Residences | 30.48m | 8s | Condoman | Standard Practice

    Yes it does. Did you get you money back in that project? He also has another called THEO which the sales office and sign are now fully covered in graffiti
  2. T

    Toronto The View Residences | 30.48m | 8s | Condoman | Standard Practice

    Not surprised it’s crashed and burned. No work for 6 months says a lot. I think they’re going to cancel all contracts.
  3. T

    Toronto The View Residences | 30.48m | 8s | Condoman | Standard Practice

    Update. No work since Oct 20. All remaining equipment removed last week. 18months in to excavation and still not finished. ⚠️ ⛔️
  4. T

    Toronto The View Residences | 30.48m | 8s | Condoman | Standard Practice

    Grove the previous builder didn’t tell the new builder that the city wouldn’t approve a Kingston road exit. So work has stopped for the last 5 weeks until the city and builder find a solution. TTC said no to moving their cables and the people on Wheeler said no to access that way. Also seems...
  5. T

    Toronto The View Residences | 30.48m | 8s | Condoman | Standard Practice

    Projects similar that started selling only a year ago have cranes up already.
  6. T

    Toronto The View Residences | 30.48m | 8s | Condoman | Standard Practice

    Yup. Work has stopped again. Nothing for a month. Still not finished excavation. @davebenoit88 Any particular reason you think this?
  7. T

    Toronto The View Residences | 30.48m | 8s | Condoman | Standard Practice

    Anyone interested in starting a Facebook group for the condo?
  8. T

    Toronto The View Residences | 30.48m | 8s | Condoman | Standard Practice

    Another row of tie backs starting
  9. T

    Toronto The View Residences | 30.48m | 8s | Condoman | Standard Practice

    Interim update: Grove builder has pulled out due to a disagreement- the signs have been taken down from the site. Wonder if/when he’s going to tell us about this?
  10. T

    Toronto The View Residences | 30.48m | 8s | Condoman | Standard Practice

    Is anyone planning to sign the amendment with the new outside occupancy date of December 2025? Not sure why we would sign away our compensation for the delay.
  11. T

    Toronto The View Residences | 30.48m | 8s | Condoman | Standard Practice

    The south end piles are almost finished. More excavation on the west end (shown here, right). Next is tie backs.
  12. T

    Toronto The View Residences | 30.48m | 8s | Condoman | Standard Practice

    Still no piles on the south end due to site complexity of building on a hill. They rebuilt a ramp to get the pile driver down to the south end. Meanwhile, excavating on the east side (shown here) so the tie backs can start. (2 levels of tie backs). Slow and steady wins the race?
  13. T

    Toronto The View Residences | 30.48m | 8s | Condoman | Standard Practice

    South view. Shoring continues. Looking north up Wheeler Avenue at Juniper.
  14. T

    Toronto The View Residences | 30.48m | 8s | Condoman | Standard Practice

    Here’s a pic of the shoring going on the south side. View looking west from an empty lot looking down onto the houses on Wheeler av.
  15. T

    Toronto The View Residences | 30.48m | 8s | Condoman | Standard Practice

    I would say it’s financial. I checked, and there are permits for Post Lofts in the city website. And there are listings on MLS to sell them. I think it’s just delayed. Just my opinion from what I see. Builder probably needed to get one off the ground before the other started.
  16. T

    Toronto The View Residences | 30.48m | 8s | Condoman | Standard Practice

    Drill bits delivered. Next the south end shoring will be finished. Girders are shown on the right. The soil has been evened out to get the shoring rig into the site. Then the excavation can finish. Some hoarding is starting to go up as well.
  17. T

    Toronto The View Residences | 30.48m | 8s | Condoman | Standard Practice

    They aren’t finished digging, but from a plan I saw, it looks like the towns will be about 1 storey up from Wheeler judging by the stairs. I was told excavation would be done early-mid April