April 19
more up on my site
The day turnout to be a very information day that confirmed what I have been saying for the year and a possible change to the pull testing. Due to the weather I ended up shooting some of the corridor that wasn't on my do list this month.
There are three different name track crews doing the work but two are own by the same company. All track work is to be completed by December this year that includes stress testing of the rails along with a number of other things. Track work to start in May for the 407 bridge, Pinewood and to the PC station as well new areas. Track crews will be working 7 days a week.
The work for Britannia intersection rework is supposedly mostly concrete work.
May will see the insulation of the overhead system starting at the OMSF along with work on the various OS poles missing or needing other work ahead of the string the OS. it been said that the pull test maybe replace with a power walking test with most or all overhead in place by year end.
Concrete is poured for the tracks between Matthew Gate and Burnhamthorpe that is waiting for the topcoat for the whole block to be pour for it.
Northbound lanes reduced to a single lane as crews were digging up the road next to the guideway for new manhole cover frames in various areas.
All track work between John St and Hillcrest fully pour in place.
The substation area west of Hurontario St on John St is ready for the arrival of the substation.
Very little has been done for the crossover track work south of Hillcrest since I last saw it.
Mobile sign for northbound traffic saying no left turn at John St starting April 23rd and saw none for the southbound
Duct work taking place on the west side of Hurontario St from Dundas St to Agnes.
All concrete poured for the tracks from King St to the southside of Floradale with track crew working on the next section toward Paisley
Looks like Paisley intersection looks ready for concrete curb to be pour follow by the base pouring/
Once Paisley intersection is done, the rest of the tracks south of it will see final work on the tracks along with forming down to the fire station driveway.
Looks like north-south tracks being installed for the wye are where the barrier wall still has to be built.
Grading of the area for the Hwy 403 ramp to Hurontario to allow landscaping.
Saw a number of cars for the ramp to Hurontario area but saw no one until I was leaving when a surveyor truck pull in.
The area from the ramp to Hurontario as well the guideway on Hurontario St has the base poured for it and waiting track work. The bullnose curb between the guideway entering Hurontario St guideway and part of the protection for the northbound traffic is inline with the south off ramp lane for Hwy 403. we will most likely see southbound traffic shift back to its nominal lanes by June. The east side curb for the Hwy 403 on ramp is poured and cover up.
What I have seen this month, 2028 will see us riding the line at some point with full testing while underway in 2027.
King Sr
Looking north from Matthew Gate
Many areas between Fairview and Central Pkwy
Fairview Station