Khamaa
New Member
We’ve hit the 65% mark for piling at the Ontario Line’s second tunnel launch shaft – that’s nearly 800 out of roughly 1,200 total piles, or structural columns, installed.Based on how long it took them to build the launch shaft at Exhibition to the actual launching date of the first TBM, I don't expect the Pape TBMs to start boring until next summer at the earliest, possibly even fall. The latest report from the Gerrard site was that half the piling has been completed. The good news is that the Pape underground segment is half as long as the downtown segment (3km vs 6km)