Either in May or June there will be a public online update of the project after ML finally goes before the 3 council. More info will be announced closer to the date.
I ended up doing an unexpected walk to Dundas today for the first time this year. Hydro has most of the wiring strung on the new westside poles. After they are working and sometime this year, all the east side poles and wires will be remove from John St to Burnhamthorpe Rd.
By the looks of things, excavation of part of construction area on the west side of Hurontario St off John St is taking place for a substation.
Bracing is being installed to hold the tracks in place from John St to south of the emergency pad is taking place with concrete to be pour first of the Cooksville Station follow by the rest of the tracks being pour.
Trackwork between John St and Hillcrest is ready to be level and pour in place. The guideway area south of Hillcrest has been clean and built to allow trackwork to be install from Hillcrest and where the tracks were place in 2025.
No work taking place for both corners of the northside of Dundas. Part of the southbound guideway curb has been rebuilt and is trap.
More up on my site.
Hydro string wires on the new westside poles
trackwork bracing taking place from where it stop in 2025 to the station
Cooksville Station Trackwork taking place
Work on the Cooksville substation
Guideway Curb a King St done the last few weeks.
The guideway curb has been cut down for the emergency turning pad
Either in May or June there will be a public online update of the project after ML finally goes before the 3 council. More info will be announced closer to the date.
I ended up doing an unexpected walk to Dundas today for the first time this year. Hydro has most of the wiring strung on the new westside poles. After they are working and sometime this year, all the east side poles and wires will be remove from John St to Burnhamthorpe Rd.
By the looks of things, excavation of part of construction area on the west side of Hurontario St off John St is taking place for a substation.
Bracing is being installed to hold the tracks in place from John St to south of the emergency pad is taking place with concrete to be pour first of the Cooksville Station follow by the rest of the tracks being pour.
Trackwork between John St and Hillcrest is ready to be level and pour in place. The guideway area south of Hillcrest has been clean and built to allow trackwork to be install from Hillcrest and where the tracks were place in 2025.
No work taking place for both corners of the northside of Dundas. Part of the southbound guideway curb has been rebuilt and is trap.
More up on my site.
Hydro string wires on the new westside poles
trackwork bracing taking place from where it stop in 2025 to the station
Cooksville Station Trackwork taking place
Work on the Cooksville substation
Guideway Curb a King St done the last few weeks.
The guideway curb has been cut down for the emergency turning pad