so , once they have reached above ground concrete pouring for each floor , is it one floor per week timing , ?? does anyone know ?? thank you
The podium section normally takes a few weeks per floor because the floor plates change, and requires alterations to the forms.

Once they get to the tower section many of the floors have the same layout, so the same form is reused. That usually allows for a floor to be done about once per week.
 
th
The podium section normally takes a few weeks per floor because the floor plates change, and requires alterations to the forms.

Once they get to the tower section many of the floors have the same layout, so the same form is reused. That usually allows for a floor to be done about once per week.
thank you for the info .....hoping there won't be a delay with the World Cup affecting keeping roads cleared , there was a news story on cbc . the firing trucks will /are doing it on Dalhousie
 