Resubmitted with Tower A (the eastern tower) reduced from 35 to 29-storeys and moderate redistributions of the unit mix, parking mix and GFA. The tower floorplate has increased from 779m² to 850m² GCA and an 8-storey volume has been incorporated into the base of the tower resulting in a slight increase in total GFA despite the height reduction. Total car parking is down from 278 to 254 while bike parking count remains unchanged.

Updated renderings:
Architectural Plans - 2025-09-16T120500.636-0.jpg
Architectural Plans - 2025-09-16T120500.636-5.jpg
Architectural Plans - 2025-09-16T120500.636-6.jpg
Architectural Plans - 2025-09-16T120500.636-7.jpg
 
A couple of quick updates here.

1) This was approved at this week's Council meeting w/o amendment.

2) No SPA has been filed; and I don't expect one soon.........see 3 below

3) The Sobeys here is getting a major renovation starting in mid-January, likely well into 7 figures, no indication of re-bannering. Given the size of investment, I would assume nothing is happening here for at least 5 years.
 

As noted above, this project won't be moving ahead in the near term.

You can see some signs of construction on the Sobeys by the entrance, this is part of the major reno I mentioned.

The exterior is getting a new appearance around the entrance.

Based on the interior, I'd say they're about 1/2 done, with a likely finish date sometime in early summer.
 