• Windows are scheduled to be installed on the second floor by the end of month
• Ground floor curtain wall installation will start in January
• Currently forming on the fifth floor with anticipated completion of forming for the entire project by April 2020
• Interior finishings is anticipated to start this month
• Streetscaping is anticipated to take place in the summer of 2020

Source - tridel.com/aquabella/live-construction-camera/