Hi, I'm on the same bout, I bought my unit in April 2023, and I got an update that Elm will complete construction in 2027, which is too late. Have you figured out any way to exit ? Please let me know
October 16, 2024
To: Counterparties (“Home Buyers”) to unit purchase agreements with Vandyk-Heart Lake
Limited (the “Company”)
Re: Update No. 7 to Home Buyers
Pursuant to the order issued by the Ontario Superior Court of Justice (the “Court”) on November 14, 2023,
as most recently amended on...
my outside ocupacy date is 2029, even though Meg pushed me to pay my last installment in April this year during the receivership, so I do not know how to fight with these giants to get my deposit back
I received this notice in my email, does it mean they will build the project without any amendment and hold the deposit for a long time? I bought the unit in April 2023 for a down payment of $ 100k