Project Essentials / dataBase – detailed project information, floor plans, renderings
Projects & Construction Thread
Lower Simcoe Ramp and New Park 
, Toronto
Developer: City of Toronto

Lower Simcoe Ramp and New Park | ?m | ?s | City of Toronto | Page 61

Discussion in 'Transportation and Infrastructure' started by jozl, Jul 3, 2015.

  1. DSC

    DSC Senior Member

    Joined:
    Jan 13, 2008
    Messages:
    7,419
    Likes Received:
    1,916
    Location:
    St Lawrence Market Area
    Oh my god, they forgot about doing the north side of Harbour Street. Heads will roll!

    Obviously they need to finish the south side first and that is what they are doing; look at the plans and renderings.
     

    Attached Files:

    Last edited: Oct 9, 2017

  2. Panontario

    Panontario Active Member

    Joined:
    Oct 23, 2011
    Messages:
    135
    Likes Received:
    78
    I don't know if your response is sarcasm or something else is wrong... But yes, I hope that they finish the North part of the stretch between York and Bay this weekend. They have 3 full days to do that.
     
  3. DSC

    DSC Senior Member

    Joined:
    Jan 13, 2008
    Messages:
    7,419
    Likes Received:
    1,916
    Location:
    St Lawrence Market Area
    You did not say you wanted the north side finished 'this weekend' and on that score you will certainly be out of luck. They need to completely rebuild the road, curbs etc and the sidewalk on the north side. They will open the south side first then shut north side and do it - I suspect it will take at least 3-4 weeks (depending on whether they need to install new pipes/wires etc;) by which time the ramp may be almost finished.
     
  4. Panontario

    Panontario Active Member

    Joined:
    Oct 23, 2011
    Messages:
    135
    Likes Received:
    78
    They managed to do just that for the South side from York to Bay and entire 4 lanes from LS to York when they closed the road for a Labour Day weekend. It's too bad if they do use this opportunity to rebuild the rest of the road now while the weather is still good.
     
  5. DSC

    DSC Senior Member

    Joined:
    Jan 13, 2008
    Messages:
    7,419
    Likes Received:
    1,916
    Location:
    St Lawrence Market Area
    They PAVED the south section oh Harbour that weekend, I think, the concrete base and the utilities under it took much longer. The north half of Harbour needs to be completely rebuilt and they seem able to do this kind of work right through to December, though it's doubtless easuer when it's not too cold or wet.
     
  6. Panontario

    Panontario Active Member

    Joined:
    Oct 23, 2011
    Messages:
    135
    Likes Received:
    78
    They paved the south side of the road between LS and Bay and rebuilt North side from LS and York during the Labour Day weekend.
    You are clearly being antagonistic in your responses while demonstrating lack of all of information on this topic. If you look just few posts up, you will see that I have provided numerous updates in this thread, and well aware of the situation. I am not going to get into a match with you.
     
    Michael62 likes this.
  7. Michael62

    Michael62 Active Member

    Joined:
    Feb 26, 2008
    Messages:
    260
    Likes Received:
    314
    Progress on the Bay/Harbour intersection continues.

    This is looking west from the pedestrian bridge, clearly shows there is no work on Harbour between York and Bay this weekend.

    looking west on Harbour.
    The concrete underlay is almost complete. Next set of pictures are of the Bay/Harbour intersection. First pic is from north east looking towards south east corner. Second pic is from south west corner looking towards north east corner. Third pic is from south east corner looking towards the north west corner.

    Hope it's not too confusing

    NE looking toward SE corner.
    SW looking toward NE corner. SE looking to NW corner.
     
    Last edited: Oct 8, 2017
  8. Michael62

    Michael62 Active Member

    Joined:
    Feb 26, 2008
    Messages:
    260
    Likes Received:
    314
    Today the intersection is being paved, and some of the lines have already been painted. They work fast!

    paving.
     
  9. jdoe1369

    jdoe1369 New Member

    Joined:
    Oct 1, 2011
    Messages:
    31
    Likes Received:
    102
    From my perch above, I've got the past week laid out so here we go:

    Oct 3: Working on the Harbour, digging a trench, doing construction stuff, and making the pretty black pavement all muddy

    IMG_20171003_175838. IMG_20171003_175851.
     
  10. jdoe1369

    jdoe1369 New Member

    Joined:
    Oct 1, 2011
    Messages:
    31
    Likes Received:
    102
    Oct 5: More trench work

    IMG_20171005_165144. IMG_20171005_165221. IMG_20171005_165254.
     
    jdee, ADRM, Michael62 and 1 other person like this.
  11. jdoe1369

    jdoe1369 New Member

    Joined:
    Oct 1, 2011
    Messages:
    31
    Likes Received:
    102
    Oct 6: The party starts. Bay/Harbour shut down, jackhammers at midnight, getting the pavement gone.

    The ceremony starts with the customary excavator parade
    IMG_20171006_210322.
    Followed by the police v. excavator showdown
    IMG_20171006_210640.

    Then comes the destruction

    IMG_20171006_213002. IMG_20171006_213222. IMG_20171006_213352. IMG_20171006_213652. IMG_20171006_223406. IMG_20171006_225345. IMG_20171006_225351. IMG_20171006_230943.
     
    jdee, ADRM, Michael62 and 1 other person like this.
  12. jdoe1369

    jdoe1369 New Member

    Joined:
    Oct 1, 2011
    Messages:
    31
    Likes Received:
    102
    Oct 6 ct'd.

    IMG_20171006_230943-ANIMATION.
     
    interchange42, jdee, ADRM and 3 others like this.
  13. jdoe1369

    jdoe1369 New Member

    Joined:
    Oct 1, 2011
    Messages:
    31
    Likes Received:
    102
    Oct 7: Digging in the sandbox

    Early morning start
    IMG_20171007_071403.

    Working all day in the sandbox
    IMG_20171007_093351. IMG_20171007_112406. IMG_20171007_173514. IMG_20171007_173526.

    Sun sets, traffic still backed up

    IMG_20171007_183058.

    Still pushing dirt; someone needs to grease the bulldozer (those squeaks were worse than the jackhammer)
    IMG_20171007_201546.

    End of Oct 7

    IMG_20171007_205533.
     
    jdee, ADRM, someMidTowner and 2 others like this.
  14. jdoe1369

    jdoe1369 New Member

    Joined:
    Oct 1, 2011
    Messages:
    31
    Likes Received:
    102
    Oct 8: Pouring concrete, laying new lines, cutting new lines

    When we awake we see the shrunken outline for the new Bay/Harbour

    IMG_20171008_074559.

    Then begins the all-day pour

    IMG_20171008_095509. IMG_20171008_113204. IMG_20171008_115626. IMG_20171008_135256.
    All poured

    IMG_20171008_184748.

    And now we cut the new concrete

    IMG_20171008_222206.
     
    interchange42, jdee, ADRM and 4 others like this.
  15. jdoe1369

    jdoe1369 New Member

    Joined:
    Oct 1, 2011
    Messages:
    31
    Likes Received:
    102
    Oct 9: Paving time

    Late start due to the rain, they start painting the lines while they're still laying asphalt

    IMG_20171009_105123. IMG_20171009_113636. IMG_20171009_125021. IMG_20171009_133111.

    Nearly done:

    IMG_20171009_142649.

    Lest we forget the trench:

    IMG_20171009_163052.
     
    ttk77, interchange42, jdee and 9 others like this.