Update:
July, 2017
The piles are in at The South Shore and the construction crew is working on forming the footings for the foundation. The preview opening of the second phase took place in early April, with broker In2ition Realty making nearly 20 sales in the second quarter and booking a number of future appointments. Occupancy is now scheduled for October of 2018. Interested purchasers should visit the off-site sales office at 225 The Queensway South in Keswick or visit www.thesouthshore.ca.
 
Update: https://fortressrealdevelopments.com/projects/the-south-shore/
January, 2018
The foundation piles and concrete footings (pile caps) have been completed. Next steps include preparations for commencement of the superstructure, including the completion and modifications of the detailed drawings, and bidding and submission of permit applications. The sales office remains open during the winter months.
 
Update: https://fortressrealdevelopments.com/projects/the-south-shore/
April, 2018
With the pile work complete at the South Shore, the development team is working on scheduling and budgets to start the above-grade construction. Bidding for the job will be ongoing in the spring, while the sales centre will be offering some unique springtime promotions for the final available units.
 