Depending on the progress of the Rigs and the stage Deep Foundations is at, it could be cheaper to just let them complete their contract instead of terminating it.
Redesign will drastically change structure, construction will stop
very unfortunate
Good Catch, you will notice that this Metrolinx is within the Skywalk,
You can see the 50 storey office tower above the skywalk at station and simcoe, there is a scheme where the skywalk existing glazing is torn down and redone
Project looks best is early morning or early evening light, especially the Chapel. Wood Fin Mockup is in the Chapel, 8 m tall !!!!
Copper is going in along Top and Bottom of Curtainwall, when finished, the South Perimeter will have a Corten Eyebrow Installed
Tile work has started at North...
I have been to this ING Building twice with a friend while she was running an errand, All i have to say is its a Bitch to get yourself onto that street, very confusing
Im not sure if they have indeed signed the main tenant, I was hearing ING was pitched, shall inquire.
Subtrade Tenders for Shoring & Underpinning, Excavation, Formwork, Reinforcing are out on the street.
This Project will get going very soon.
Demolition will start soon, the Existing Facades will be retained and braced while the interior slabs will be demo'd down. The Massive X jacks is being detailed by Walters of Hamilton and the Structural Glass that surrounds the 5 storey atrium is being...
Prequalification for Landscape Contractors, Go Aldershot!!!
https://wx.toronto.ca/inter/pmmd/calls.nsf/0/B528EE72E3859ED185257893005AB709?OpenDocument
Tender - Prequalification Call number: 3717-11-5032
Commodity: Construction Services, Landscape Construction